Longville Seeks DNR Action as Girl/Woman Lakes Levels Continue to Fall

By Dave DeLost Publisher, Pine Cone Press-Citizen

The City of Longville is seeking assistance from the Minnesota Department of Natural Resources (DNR) as concerns continue over falling water levels on Girl Lake following construction of the Rock Arch Rapids project at the lake’s outlet.

The city met Friday, October 2 with Barr Engineering to discuss the situation and has asked the firm to provide technical assistance in determining whether the newly constructed rock arch rapids has changed the outlet conditions and contributed to lower-than-normal lake levels.

In a Sept. 24 proposal to the city, Barr Engineering said there is “strong evidence” that the Rock Arch Rapids, as constructed, has reduced the normal upstream lake level. The proposal noted that the DNR has pointed to local drought conditions as the primary cause of the reduced lake levels. Barr proposed reviewing project plans, surveys, construction records, lake-level data and hydrologic information, as well as inspecting the outlet and evaluating the relationship between lake elevation and discharge.

The proposed engineering review would also examine whether the Rock Arch Rapids was constructed substantially in accordance with its design and whether any differences could affect lake levels or hydraulic performance. The estimated cost of the initial work is $37,100.

Barr’s Joel Toso, PhD, PE, a senior water resources engineer, has more than 40 years of experience involving hydrologic and hydraulic modeling, flood forecasting and dam engineering. He also taught applied hydrology and hydraulics at the University of Minnesota for nearly 20 years.

Continue reading at the Pine Cone Press-Citizen
 